Charlotte Crossing Construction Project

ATLANTA, GA

Beginning today, Monday, October 9th, our Charlotte Intermodal Facility will begin rail crossing construction that will last through Thursday, October 12th. The track-specific daily schedule of crossing construction is outlined below:   

  • Monday 10/9 – Track
  • Tuesday 10/10 – Track 2
  • Wednesday 10/11 – Track 5
  • Thursday 10/12 – Track 5

 

While drivers will not be impacted today, beginning tomorrow drivers should expect temporary traffic pattern changes due to the construction. The Charlotte terminal map is attached with crossings indicated by vertical arrows as reference.    

No departure, availability, or gate delays are expected because of the construction. Drivers should maintain safe speeds, be aware of construction crews and vehicles, and obey all signage and temporary changes in traffic patterns while on terminal.

 

We encourage drivers to take advantage of our ExpressNS+™ Mobile Application which streamlines gate and terminal processes for our drayage community. With ExpressNS+™, drivers can verify billing, submit pre-gate information, obtain parking and pickup locations, receive electronic interchange receipts, and submit bad order information. More information on ExpressNS+™ can be found by scanning the QR code below or by visiting www.nscorp.com/intermodal/ExpressNS.