Project Schedule
August 7, 10, 11
- Phase 1 – WE Crossing
- Phase 2 – Track 14 West End
August 12–14
- Phase 3 – Track 14 East End
- Phase 4 – I-81 Bridge / Dumpster Area to 14 East End Crossing
- Phase 5 – Track OWB West End
August 17–20
Phase 6 – Track Canal / WHS Entrance
August 21–25
- Phase 7 – Track OWB East End
- Phase 8 – GI8
- Phases 9-12 – GI8 / Duckville Entrance
August 26–28
- Phase 13 – Track 18 to McClay St Bridge
During construction, traffic patterns and access routes may be temporarily adjusted within the terminal. We ask that all drivers and visitors follow posted signage and the directions of on-site personnel to ensure everyone’s safety, and to help maintain efficient terminal operations.
No shipment departure or availability delays are expected during the project. We appreciate your patience and cooperation as we complete these improvements. Updates will be provided if the schedule changes due to weather or other unforeseen circumstances.