Project Schedule
August 18 – September 7
- Phase 1A – Lot TS03
- Phase 1B – Main Crossing
September 9 – September 29
- Phase 2A – Lot TS02, to include Lot 45A, this will restrict access to Lot 4D
- Phase 2B – Entrance to Lot 4D (rear lot)
September 30 – October 23
- Phase 3 – TS01, this will restrict access to Lot 45A
October 23 – November 10
- Phase 4A – Inbound Entrance, we will use the outbound lane as an entrance and exit lane
- Phase 4B – Outbound Entrance, we will use the inbound lane as an entrance and exit lane
October 28 – November 25
- Phase 5 – Lot 53 & Lot 20
During construction, traffic patterns and access routes may be temporarily adjusted within the terminal. We ask that all drivers and visitors follow posted signage and the directions of on-site personnel to ensure everyone’s safety, and to help maintain efficient terminal operations.
No shipment departure or availability delays are expected during the project. We appreciate your patience and cooperation as we complete these improvements. Updates will be provided if the schedule changes due to weather or other unforeseen circumstances.