A 26-hour window. Six major projects. One team.

Portland Avenue project in Louisville The Portland Avenue project upgraded a unique track configuration supporting train movements through one of Louisville's busiest rail operating areas.

Strategic infrastructure improvements completed during a single planned work window strengthen reliability across a key freight corridor in Indiana and Kentucky.

 

During a recent 26-hour maintenance window on Norfolk Southern's W Line, which supports intermodal and automotive traffic between Midwest and Southeast markets, railroaders completed six major infrastructure projects across southern Indiana and Kentucky. The coordinated effort included bridge replacements, track and ballast renewal, upgrades to a complex rail junction, and preparation for a future automated railcar inspection portal.

 

Top Takeaways

  • Norfolk Southern teams from Engineering and Transportation completed six major infrastructure projects during a single planned work window on the W Line in Indiana and Kentucky.
  • Cross-functional planning and execution improved infrastructure reliability while avoiding five additional maintenance windows.
  • The work strengthened bridges, renewed track, and increased operating speeds, supporting long-term network performance.

Why it matters

 

Every planned maintenance project requires balancing infrastructure needs with customer service and network performance.

 

According to David Taylor, Division Engineer, bundling multiple projects into a single work window enabled NS to complete significant infrastructure work while avoiding five additional maintenance windows that would have affected operations and customers. The effort also provided an opportunity to complete additional maintenance activities including rail replacement, welding, ditching, and grinding.

 

"Success started long before the work began," said Taylor. "Our teams brought together ideas from across the railroad, assigned strong project leaders and worked through challenges early to ensure safe, efficient execution."

 

Major improvements across the corridor

 

Work completed during the 26-hour work period included:

  • Three bridge replacements in Indiana and Kentucky
  • Track and ballast renewal through the English Tunnel in Indiana
  • New track installation in Bretzville, Indiana, supporting an automated railcar inspection portal planned for 2027
  • Upgrades to a complex rail junction supporting train movements at Portland Avenue in Louisville, Kentucky

By bundling multiple projects into a single phased approach, teams maximized available track time and delivered more value from planned infrastructure work.

 

One of the most technically complex projects involved replacing the Portland Avenue diamond crossover and four power switches. The unique track configuration supports multiple yard, mainline, and branch-line movements, making precision planning and installation critical.

 

The bridge replacement in Shelbyville, Kentucky, included track realignment through a challenging curve, creating a smoother route that eliminated a longstanding maintenance issue and increased train speed from 30 to 35 mph. The new alignment is capable of supporting 40 mph in the future.

Shelbyville project span setting As one of three bridge replacements completed, the Shelbyville project replaced an existing four-span bridge with a new two-span design spanning 130 feet.

Built on preparation and collaboration

 

The effort required months of planning and brought together about 115 employees from Engineering and Transportation. Teams coordinated materials, labor resources, and train operations to complete the work safely while minimizing impacts to service. Specialized track components were also assembled in advance at NS’ Roadway Material Yard in Roanoke, Virginia, supporting efficient installation once the field work began.

 

Transportation and the Network Operations Center (NOC) leaders managed train movements before, during, and after the planned maintenance, helping ensure the railroad recovered efficiently as the line returned to service.

 

A stronger railroad for the future

 

The W Line improvements strengthen bridges, track and critical operating infrastructure while reducing future maintenance needs and supporting long-term network reliability. The project also demonstrates how thoughtful planning and coordinated execution can maximize available track time and deliver meaningful improvements for customers and the communities NS serves.

By Brett Willi, Senior Communications Manager

 

Brett Willi leads internal communications for Norfolk Southern, focusing on safety, compliance, operational excellence and employee engagement. He also oversees communications for Engineering and Mechanical. Brett joined NS in 2025, with 20 years of strategic communications, digital content and analytics expertise.

 

 

 

SUBSCRIBE TO MEDIA ALERTS

Sign up for email alerts on the latest news and stories from Norfolk Southern.

Media Contacts

Are you a member of the media? Contact our media relations team.